Timesheet and Non-Billable Time

Have you ever been working on a project and want to show non-billable time?  By now you know that you can easily do this with Microsoft Project Online or Project Server’s PWA using the timesheet.

When I click on the Actual Non-Billable row for this particular task I cannot enter time.  Why not?

timesheet

First, you need to have Non-Billable selected for your timesheet.
On the Options tab select the Non-Billable option and you will see the Actual Non-Billable row for all projects.  Note You will not be able to enter non-billable time for Administrative tasks or Manually Scheduled tasks

non billable time

If you come across a project task that does not let you enter in Non-Billable time in your timesheet make sure that the task has a task mode of Automatic vs Manual and that the project is scheduled.

actual non billable

There you go folks.  Hope this little quick ‘gotcha’ serves you and your teams well.
Cheers and let us know if you have any other items you need help with.  Just contact us.


PPM Works is a full service Microsoft Project and Portfolio Management consultancy, focused on Microsoft Project Server and Microsoft SharePoint platforms.  We believe in partnering with our clients to exceed expectations and build long lasting rewarding partnerships. We are continuously building a knowledge base of multiple tips, tricks and solutions to make your use of Microsoft Project Pro as smooth as possible. Contact us for more information.

Stay updated with the latest of Project Online/Server 2013 with us: Subscribe. Check our future events!

Subscribe to our webcast email list for updates on our upcoming webinars! 

Visit our FAQ Page for access to our tool box.