Reinstalling Workflow Manager 1.0
We had working Workflow Manager farm in Project Server 2013 environment which stopped working after refreshing the PWA environment using database attach method. We resolved the issue by Reinstalling Workflow Manager 1.0 in Project Server 2013 Farm.
We were getting below error while creating new Projects.
Error:
General
- Error:
- WorkflowCannotStartWorkflow (35100). Details: id=’35100′ name=’WorkflowCannotStartWorkflow’ uid=’2638469d-653c-e611-811d-0050569a688c’.
- Queue:
- GeneralQueueJobFailed (26000) – WorkflowStartWorkflow.WorkflowStartWorkflowMessage. Details: id=’26000′ name=’GeneralQueueJobFailed’ uid=’2738469d-653c-e611-811d-0050569a688c’ JobUID=’0428d69c-653c-e611-811d-0050569a688c’ ComputerName=’44493b58-ff91-4783-b43b-6a04dd079a84′ GroupType=’WorkflowStartWorkflow’ MessageType=’WorkflowStartWorkflowMessage’ MessageId=’1′ Stage=” CorrelationUID=’55418a9d-3a72-102c-79a8-45b26251b429′. For more details, check the ULS logs on machine 44493b58-ff91-4783-b43b-6a04dd079a84 for entries with JobUID 0428d69c-653c-e611-811d-0050569a688c.
We tried different troubleshooting steps but none of it helped to resolve the issue. Finally issue resolved by uninstalling and reinstalling Workflow Manager 1.0 Below are the detailed steps.
Uninstall Workflow Manager
Step1 : Leave the Farm
-
-
- Log on to the server on which you have installed and configured workflow Manager.
- Launch Workflow Manager Configuration Wizard
- When the Workflow Manager Configuration Wizard page appears, click Leave Farm. The Leave Farm page appears
- Click on Apply.
-
Step2: Uninstall Workflow Manger and other Application
-
-
- In the Control Panel window, under Programs select Uninstall a Program.
- Find the following items in the program list and, for each item, click Uninstall on the menu bar above the program list.
-
-
-
- Workflow Manager 1.0
- Workflow Manager 1.0 Client
- Service Bus 1.0
- Windows Fabric
-
Step3: Delete Workflow related Databases.
- Take Backup of any workflow related databases.
- Use SQL Management Studio to remove the databases that were associated with Workflow Manager. These databases are:
- WfManagementDB
- SbGatewayDatabase
- SBContainer01
- WFInstanceManagementDB
- WFResourceManagementDB
- SBManagementDB
Install and Configure Workflow Manager
Step 4: Install Workflow Manager 1.0
Click the contextual installation link. This will initiate the installation steps for Workflow Manager
Step 5: Configure Workflow Manager
- Open the Start menu.
- In All Programs, go to Workflow Manager 1.0. Click the Workflow Configuration shortcut to start Workflow Configuration Wizard
- Click on “Configure Workflow Manager with Default Settings”
Steps 6: Register the workflow Manager service
Register-SPWorkflowService -SPSite ‘https://myhost/mysite’ -WorkflowHostUri ‘http://workflowhost:12991′ –force
Hope this helps. Contact us with any questions
PPM Works is a full service Microsoft Project and Portfolio Management consultancy, focused on Microsoft Project Server and Microsoft SharePoint platforms. We believe in partnering with our clients to exceed expectations and build long lasting rewarding partnerships. We are continuously building a knowledge base of multiple tips, tricks and solutions to make your use of Microsoft Project Pro as quick and easy as possible. Contact us for more information.
Stay updated with the latest of Project Online/Server 2013 with us: Subscribe. Check our future events!
Subscribe to our webcast email list for updates on our upcoming webinars!
Visit our FAQ Page for access to our tool box.