Will changing Planner data maintain the tasks predecessors & successors?
Yes, the dependencies (both predecessors and successors) that are set in Project and go to Planner will remain in Project when the data syncs back from Planner to Project. When possible the task will remain automatically scheduled. However there are some conditions, such as setting a start/finish date [...]