Does the Project to Planner Sync Tool work with Project Professional?
The sync will work if you are using Project Professional and save/store your projects in Project Online.
The sync will work if you are using Project Professional and save/store your projects in Project Online.
By default, the following fields can be changed on either end: Task Title Task Start Task End (Due Date) Task % Complete (Progress) Task Description (Notes) Task Bucket Name Task Priority Task Labels Task Assignments
Yes, Planner does not have security controls to prevent this.
The sync solution will not delete tasks on either end. If a Planner Task is deleted the task-level sync field in Project indicates “Deleted” If a Project Task is deleted the planner task title is appending with “|Deleted”
There are separate configuration options to prevent Planner Task updates from updating: Project Task Title Project Task Start and Finish Project Task % Complete Project Task Assignments